A window to pour concrete in Rutherford

How to pour 200m3 of concrete over a 1000m2 slab

How to pour 200m3 of concrete over a 1000m2 slab in the middle of winter…..? start early and finish late !

This week, our Rutherford project completed the second major concrete pour on site for the new Storage King project in Rutherford.  The Weather Gods were finally a little kinder and after careful planning with Di Prinzio Concreting it was smooth sailing.

Setting up pre-dawn and finishing well after the sun set, the team managed to get the pour completed in 1 day.

This project consists of 2 x purpose-built stand-alone 2 storey buildings for a new Storage King facility.